Senior Years Campus

The build is moving head at great pace:

  • On-site works are progressing ahead of Program and handover to the College is on track to enable opening for Semester 2 2026
  • The Level 2 slab pour occurred on 23rd September 2025
  • Level 2 precast concrete install was completed on 1st October
  • The Level 3 slab pour was completed on the 15th October and the Level 4 slab will be poured on 30th October
  • The Façade install is targeted to commence in November 2025, following issue of Building Permit 4
  • The Substation Room has been stripped and a CitiPower inspection has been scheduled for late-October 2025, with substation delivery expected in early-2026
  • The project team are continuing to progress the furniture and wayfinding design with meetings to look at the furniture recommendations scheduled for 24th October

A timelapse video has been prepared up to the erection of the 2nd Floor:


View from 2nd floor Current site 15th October pre level 3 slab pour