Update
Senior Years Campus
The build is moving head at great pace:
- On-site works are progressing ahead of Program and handover to the College is on track to enable opening for Semester 2 2026
- The Level 2 slab pour occurred on 23rd September 2025
- Level 2 precast concrete install was completed on 1st October
- The Level 3 slab pour was completed on the 15th October and the Level 4 slab will be poured on 30th October
- The Façade install is targeted to commence in November 2025, following issue of Building Permit 4
- The Substation Room has been stripped and a CitiPower inspection has been scheduled for late-October 2025, with substation delivery expected in early-2026
- The project team are continuing to progress the furniture and wayfinding design with meetings to look at the furniture recommendations scheduled for 24th October
A timelapse video has been prepared up to the erection of the 2nd Floor:

View from 2nd floor Current site 15th October pre level 3 slab pour
Jonathan Stringfellow
Business Manager